Project Brief
As air handling and extraction units had to remain on the roof during the application, and with flats in close proximity to the back of the building, a product with low odour which would allow a guarantee to be issued on completion. Proteus Waterproofing supplied 250m2 of its Pro-System waterproofing membrane to provide a long term guarantee.

Key Requirements: Health and Safety
As Pro-System is cold installed, it meets all health and safety criteria for occupied buildings and minimises risk of fire. The low odour application of Pro-System also allowed Proteus’ Licenced Contractor to minimise disruption to operatives, employees and the milling processes.

Key Requirement: Seamless waterproofing
Due to the difficult access, detailing aspects and complex nature of the roof, Proteus Waterproofing worked in close partnership with the licensed contractor to successfully deliver the project to a very high standard.

Key Requirement: Long term performance
Pro-System waterproofing system offers 10, 15, 20 and 25 year durability options which are also available with independently provided insurance.